Here is the latest time-lapse video from the M5 Olbury Viaduct project. This was taken in December and features a period of one week where there was heavy snow on the southbound carriageway. It was not possible, and would have been fairly unwise, to apply road salts to the work areas, hence we were unable to undertake any concrete repairs that week.
Following the December snow and Christmas shutdown, the project is fully up and running again, with a big push on production. We have brought in warm air units to enable pouring and curing of deck repairs during the current low temperatures.